How to estimate concrete for strip footings
For rectangular trench foundations, multiply the total run length by the specified footing width and poured depth. This gives cubic metres before any quantity allowance. Stepped footings and varying trench widths should be measured as separate sections and added together.
Worked example
A 12 m continuous run, 600 mm wide and 300 mm deep gives 12 × 0.6 × 0.3 = 2.16 m³. With 10% extra, this becomes about 2.376 m³.
Frequently asked questions
Can this design my foundations?
No. It only estimates concrete volume. Footing dimensions and reinforcement should follow approved plans and professional advice.
Do I enter excavation depth?
Enter the actual depth of concrete to pour, which may differ from the total excavation depth.
Can I calculate stepped foundations?
Measure each step as a separate rectangular section and add the results.